ROAD CLOSURES |
|
STREET NAME
|
FROM/TO
|
REASON/DURATION
|
|
ROAD OPENING: |
|
NEW ROAD CLOSURE: |
|
EXISTING ROAD CLOSURE: |
|
HALLS LANE WEST (Downtown)
|
GAUKEL STREET TO ONTARIO STREET |
HYDRO VAULT REBUILD
Tentative: Mar 31, 2010
|
|
HALLS LANE (Downtown)
|
BENTON STREET TO SEIGNOR LANE |
PARKING GARAGE CONSTRUCTION
Tentative: Apr 30, 2010
DELIVERIES ONLY |
|
UPCOMING ROAD CLOSURE: |
|
TILT DRIVE
|
GROH DRIVE TO APPLE RIDGE DRIVE |
WATERMAIN + SANITARY CONNECTIONS
Start: MARCH 15, 2010
Duration: 3 DAYS
LOCAL TRAFFIC ONLY - DAYTIME CLOSURE ONLY |
|
ROBERT FERRIE DRIVE
|
DOON SOUTH DRIVE TO TILT DRIVE |
WATERMAIN + SANITARY CONNECTIONS
Start: MARCH 15, 2010
Duration: 3 DAYS
LOCAL TRAFFIC ONLY - DAYTIME CLOSURE ONLY |
|
DAVID STREET
|
JUBILEE DRIVE TO JOSEPH STREET |
BUILDING DEMOLITION
Start: MARCH 18, 2010
Duration: MARCH 18 - 31, 2010
|
|
KING STREET (Downtown)
|
YOUNG STREET TO WATER STREET |
KING STREET RECONSTRUCTION STAGE 4
Start: APRIL 6, 2010
Duration: 14 WEEKS TENTATIVELY
|
|
PARK STREET
|
GREEN STREET TO STRANGE STREET |
ROAD RECONSTRUCTION STAGE 1
Start: APRIL 6, 2010
Duration: 5 WEEKS
FULL INTERSECTION CLOSURE OF PARK STREET AND GLASGOW STREET |
|
GLASGOW STREET
|
YORK STREET TO GRUHN STREET |
ROAD RECONSTRUCTION OF PARK STREET STAGE 1
Start: APRIL 6, 2010
Duration: 5 WEEKS
FULL INTERSECTION CLOSURE OF PARK STREET AT GLASGOW STREET |
| TOP |